At Superior Choice Granny Flats we take pride in knowing our building processes are streamlined and stress free for our customers.

With over 20 years in the Perth building industry, we do not cut any corners or use cheap materials. All permits are pre-arranged, and you will be updated with each phase and will be delighted with your new granny flat!

Ready to get started?

Our step by step process below shows you just how simple it is to get started on building your new granny flat. Ready to talk to one of our granny flat experts? Call Superior Choice Granny Flats today on (08) 9468 3501, or visit our Canning Vale showroom.

QUOTE & ADMIN
QUOTE & ADMIN

Quote Acceptance & Signup/Deposit  (4 weeks)

  • Preparation of paperwork job submitted
  • Job Approved by management
  • Job submitted to Drafting
  • Final drafted results and addendum signed and accepted by client
  • Job certified, indemnity insurance and processed through to shire
    ** Soil report and Survey Plan required

Building Licence Received  (4 – 12 weeks)

First inspection by registered builder

CONSTRUCTION
CONSTRUCTION

Site works  (1 Week)

  • Removal of green matter
  • Removal of existing soil and supply correct amount of clean fill to achieve compaction
  • Compaction certificate plus white ants certificate
  • Plumber pre-lay
  • Concrete slab pour
    ** 2 Weeks cure time for concrete

Granny Flat Construction  (Lockup 2-3 Weeks)

  • Granny Flat Installers
  • Plumber Pre-lay
  • Electrician Pre-lay

Second inspection by registered builder

FITOUT
FITOUT

Fitout  (1-2 Weeks)

  • Gyprock
  • Undercoat walls and ceiling
  • Tiler – screed weatherproof and lay tiles
  • Kitchen
  • Bathroom
  • Carpenter – Window and door trims plus skirtings
  • Plumber fit off
  • Electrician fit off

Third Inspection by registered builder

COMPLETION
COMPLETION

Extra Works

  • Flooring
  • Painting inside and out
  • Window treatments

Final inspection from registered builder